A petition has been filed in the Supreme Court on behalf of the Karnataka government objecting to Tamil Nadu using surplus Cauvery water flowing from Karnataka for other projects on its own and seeking an order to stop the Cauvery (Kattalai) - South Vellar - Vaigai - Gundaru river linking project works. The Tamil Nadu government and the Central government have been included as respondents in this case.
In this matter, which has been pending before the Supreme Court since 2021, a petition prepared by senior advocate Mohan V. Katarki and the state government’s chief advocate Sashi Kiran Shetty on behalf of the Karnataka government was recently filed in the Supreme Court through advocate Nishanth Patil. The details are as follows:
An order should be issued to prohibit the implementation of the Cauvery–South Vellar interlinking project (the small river flowing through Tiruchi and Pudukkottai) and the related works, and to demolish the already completed Cauvery, Vaigai, and Gundaru structures. Tamil Nadu had sought the Union government’s “in-principle approval” and national project status for this project on Jan. 5, 2021. When Karnataka had already filed a case challenging the legal validity of this project, the Union government told the court that “no such approval has been granted for the project so far. Therefore, interim relief is not necessary,” and Karnataka’s interim petition was dismissed on Jan. 20 last year.
However, in an order passed by the Madurai Bench of the Madras High Court on August 1, 2024, while hearing a writ petition, it was noted from the status report filed by the Tamil Nadu government that a part of the first-phase works has been “under way since 21.01.2021.” Since this has now come to light, this new petition has been filed in the Supreme Court.
In this matter, several constructions in the first phase have been completed, and land has also been acquired for the next phase of work. However, the Tamil Nadu government did not disclose any of these details during the earlier hearing in the Supreme Court.
Tamil Nadu cannot undertake any work on this project without policy-level approval from the Central government. The work already carried out is illegal. Last year, the Karnataka government wrote to the Tamil Nadu government on March 10 and September 9, asking it to stop those works immediately.
Tamil Nadu has calculated that about 8.60 TMC of surplus water in the Mettur dam can be used (on the basis of 50% reliability). By doing so, Tamil Nadu’s unilateral use of the surplus Cauvery water generated in Karnataka could pave the way for claiming rights over that water in the future. As a result, Karnataka’s rights over the surplus water may be affected.
In this matter, Tamil Nadu’s argument that additional water will be available under the National Water Development Agency’s (NWDA) Peninsular Rivers Linking Project is not valid. According to the NWDA’s detailed project report of December 2023, the Godavari (Inchampalli)–Cauvery linking project will be completed before the Cauvery basin, and the amount of water allocated to Tamil Nadu has also been reduced from 83.27 TMC to 40.93 TMC.
Therefore, along with restraining the first-stage, second-stage, and third-stage works, Tamil Nadu should be prohibited from diverting floodwater from Mettur to the Sarabanga sub-basin, and from diverting Cauvery water under other projects, including the new barrage at Mayanur, the barrages and causeways to be built across the Cauvery and Kollidam rivers. The Karnataka government has urged in its petition that the Central Government should be directed to either refrain from considering Tamil Nadu’s 2021 request or declare the Cauvery-Vaigai-Gundaru link project as a national project.