Chennai Metro Rail administration said on Monday (Nov. 23) that the work of installing U-guards between Koyambedu Market and Alandur has been completed.
In this regard, the Chennai Metro Rail administration said in a press release:
As a major milestone in the second phase of the Chennai Metro Rail Project, on Corridor 5, the work of installing all U-girders on the approximately 9.5 km-long elevated stretch from Koyambedu Market Metro to Alandur Metro has been successfully completed. The last U-girder was installed yesterday (22.11.2026) on Pallavaram Road between Butt Road and Kathipara. This final U-girder was successfully installed using two high-capacity hydraulic cranes, each with a lifting capacity of 550 metric tons.
A total of 606 U-girders have been installed on this route. Their lengths range from 15 meters to 33.33 meters. The average weight of each U-girder is about 135 metric tons. Depending on the terrain and its requirements, the U-girder installation work was carried out using various methods, including launching girders and high-capacity hydraulic cranes.
Traffic congestion, utility cables and pipelines running both underground and overhead, severe space constraints, and difficult construction conditions prevailing in places such as Kaliyamman Koil Street, Butt Road, and Pal Wells Road were among the major challenges on this route. In addition, the integrated flyover located on Mount Poonamallee Road further complicated the work; as a result, the girder installation work was extremely challenging.
The final U-girder installation work in the section between the two pillars P399 and P400 on the elevated corridor was highly challenging and required an unconventional engineering solution.
There was not enough space to park two high-capacity cranes in the usual way. To address this, the project team adopted an innovative crane parking strategy. Accordingly, one crane was parked within the church premises, and the other was parked on the nearby narrow street. By exchanging information through walkie-talkies, the work of lifting and installing the U-girder was carried out without any interruption, with precise coordination.
Another major challenge was encountered in the section between pillars P380 and P381 on Paul Wells Road. Along with the severe space constraints in that area, there was not enough room to park the cranes needed to install the U-girders on the elevated track, as a school and residential buildings were located nearby.
To address this challenge, the project team temporarily used part of the school campus and carried out the work of positioning cranes and installing U-girders. For this purpose, the connecting pathways between the school’s compound wall and buildings were demolished. A condition was imposed that these works had to be carried out only during the Vijayadashami holiday period, and all affected structures had to be restored before the school reopened. As a result, the project team was given a very short time frame.
Moreover, the high-capacity cranes with a lifting capacity of 550 metric tons that were to be used for this work were unable to reach the required distance. Following this, a special crane with a lifting capacity of 1,000 metric tons was identified and brought in specifically for this task.
Such diverse challenges and obstacles were successfully overcome by the project team through precise planning, innovative engineering solutions, excellent coordination, collaboration with various stakeholders, timely relocation of utility infrastructure, traffic management, road diversions, and the timely arrangement of necessary resources. It further notes that, through this, complex infrastructure works in a highly congested urban environment have been successfully completed.
Chennai Metro Rail Project – another milestone in Phase II works!
— Chennai Metro Rail (@cmrlofficial) November 23, 2026
On Corridor 5, the installation of 606 U-Girders on the 9.5 km elevated section from Koyambedu Market to Alandur has been successfully completed.#சென்னைமெட்ரோ #CMRL #PhaseII #Corridor5… pic.twitter.com/0wvsJ2KfhA
