The central government's public sector enterprise, Neyveli Lignite Corporation (NLC India Ltd), has been accused of engaging in various environmental violations over the past few years. In this regard, the Comptroller and Auditor General of India (CAG) conducted an audit of NLC's operations from 2017-18 to 2022-23. The findings of this audit were submitted to Parliament with evidence earlier this month. According to the report, NLC, which operates lignite mines and thermal power plants in Cuddalore district of Tamil Nadu and Rajasthan, has been functioning without the necessary environmental clearances since...

It has been reported that many violations have occurred due to the improper maintenance of the thermal power plants. We contacted Sundar Rajan of the Friends of the Earth organization with the question, "What issues are mentioned in the NLC CAG report?" Sundar Rajan, who began to elaborate on the severity of this problem, said, "Neyveli Lignite Corporation operates brown coal mines and thermal power plants in Neyveli, Cuddalore district of Tamil Nadu, and in Barsingar, Rajasthan. The CAG audited the operations of this company from 2017-18 to 2022-23, and...

The report was submitted to the Parliament in February. The CAG has substantiated various allegations with evidence. In 2017, the Supreme Court ordered that all projects that had received environmental clearance under the 1994 Environmental Impact Assessment (EIA) notification must obtain clearance again under the 2006 EIA notification. NLC: Weekly ongoing strike - Will the demands of the Jeeva labor union be met?! NLC's Mine-II had received environmental clearance in 1994 under the Environmental Impact Assessment (EIA). Therefore,

There was a need to reapply for the environmental impact assessment. However, the NLC company did not obtain that permission. Finally, the matter was resolved in the Chennai High Court, and only in September 2023 was NLC's application accepted for consideration. The company operated without permission from 2006 to 2016. According to the conditions of the environmental clearance granted for Mine-I, the soil and rocks excavated during mining should be dumped at a 28-degree slope with a height of 20 meters. However, contrary to the rules, soil has been dumped to a height of 50 meters.

CAG has pointed out that excessive rainfall could cause the soil pile to collapse. Similarly, according to the environmental permit granted for Mine II, the height of the dumped soil and rocks should not exceed 65 meters with a slope of 28 degrees. However, contrary to this condition, soil has been dumped up to a height of 120 meters. As a result, the soil has slipped and covered nearby canals and agricultural lands. NLC issue: The judge expressed anguish... Expansion works continue on farmlands - what is happening?! Due to the negligence of the NLC company in the years 2012, 2013, 2015, and 2018, such accidents have continued repeatedly.

After the continuous protests by the farmers, the NLC company has provided compensation amounting to Rs. 2.18 crore to the farmers. Large-scale specialized mining equipment (SME) is used in the mines to excavate the land, remove the soil, and transport it. The lifespan of these machines is between 100,000 to 137,500 working hours. The NLC management had decided to refurbish the outdated machines and use them for an additional 15 years. However,

Out of the total 72 SME machines, there is no record of how many hours 26 SME machines were used. Among the 46 SME machines for which records were maintained by N.L. Sime, 15 SME machines were used without being refurbished even after they became obsolete. Eight SME machines were refurbished only after 11 years of being obsolete. Four SME machines were refurbished after becoming obsolete and continued to be used even after 15 years had passed since then.

Even after purchasing replacement machines for 2 SME machines between 1961 and 1966, they have been used. Numerous accidents have occurred in NLC mines due to outdated machines. A 2009 investigation conducted by the Mine Safety Officer revealed that "accidents and fatalities occurred due to improperly maintained machines." The CAG report also highlighted the shocking fact that no safety inspections were conducted on 12 outdated machines. Furthermore, out of the 12,835 hectares identified by NLC for mining, only 9,180 hectares of land have been utilized by NLC.

It has been acquired. As of March 2023, 5,880.34 hectares of land have been excavated. 3,253.47 hectares of land have been used for soil dumping. Accordingly, only 46.19 hectares of land remain unexcavated. NLC: 25,000 acres acquired: What are the problems caused by NLC? - What do the protesting people say?! Friends of the Earth Sundarrajan. There is information that NLC is making efforts to acquire more land. The surrounding local people have already strongly opposed the allocation of land to this company. It has been found that the three thermal power plants operating in Neyveli cannot be run at full production capacity due to defects.

As a result, a total loss of Rs. 23,539.9 crore has occurred. Due to faults in these three thermal power plants alone, power generation was halted 742 times over six years. This led to a loss of 14,538.66 MU of electricity production. In NLC thermal power plants, a total of four fire accidents occurred in the years 2001, 2016, 2017, and 2019. In the two accidents that happened in 2020 alone, 20 people lost their lives. In the investigation conducted on this matter, the CAG pointed out that "the cause of the fire accidents was the failure to properly remove the highly heated lignite dust." If lignite dust had been continuously removed, these accidents could have been prevented. This is entirely the responsibility of NLC.

Accidents that occurred solely due to administrative negligence. NLC, a public sector company, has been operating irresponsibly and negligently just as no public sector company should. The farmers who have given their lands to this company are facing countless hardships and are fighting for justice. Due to illegal activities, the surrounding villages' soil and water resources are being destroyed, posing a threat to the health of the people. The government must take action against NLC, which is operating in this harmful manner. "Tamil Nadu has developed to a level that can compete with world countries!" - Stalin's pride.


Tanglish

Madhthiya arasin pothuthurai niruvanamana Neyveli Nilakkari Niruvanam (NLC India Ltd), kadanda sila aandukalakap palveru sutruchchuzhal vidhimeeralgalil eedupattullathurukk kutram saattappadugiradhu. Ithu thodarbaaga 2017-18 mudhal 2022-23 varaiyilana kaalagattathil N.L.C niruvanathin seyalpaadugalai Indiyath thalaimai kanakku kattupattalar (CAG) aayvu seidhu. Andha aayvin mudivai indha maatham naadalamandramathil aadharangaludan samarppithirukkiradhu. Andha arikkaiyil, `Tamilnaatin Kadalur maavattathilum, Rajasthanilum nilakkari surangangal matrum analmin nilaiyangalai iyakki varum N.L.C niruvanam, uriya sutruchchuzhal anumathiyinri seyalpattadhu mudhal,

Analmin nilaiyangalai muraiyagap paraamarikkatha thavariyathu varai pala vidhimeeralgalais seidhaludhu' enath therivikkappattirukkiradhu. ENLC'CAG arikkaiyil ennnenna vivakaarangal kurippidappattirukkindrana' endra kelviyudan Poovulagin nanbargal amaippin Sundara Rajanai thodarbugondom. Indha prachanaithin theeviraththanmaiyai virivagap pesath thodangiya Sundara Rajan, ``Neyveli nilakkari niruvanam pazhuppu nilakkari surangangal, analmin nilaiyangal ullithavatrai Tamilnattin Kadalur mavadaththin Neyveliyilum, Rajasthan maanaththin Parsingkarilum iyakki varugiradhu. Indha niruvanaththin 2017-18 mudhal 2022-23 aandugalukku idaiyeyana seyalpaadugalai CAG aayvu seythu,

Andha arikkaiyai Pibruvari maadham naadaalumandratthil samarppiththadhu. Adhil palveru kutratchaattugalai aathaaraththudan ambalappaduththiyirukkiradhu CAJ.2017-um aandu uchcha neethimandram, `1994-um aandu veliyana sutruchchuzhal thaakka mathippeettu arivikkaiyin keezh, sutruchchuzhal anumathi petra anaiththu thittangalukkum, 2006-il veliyana sutruchchuzhal thaakka mathippeettu arivikkaiyin keezh meendum anumathi pera vendum' ena uththaravittirundhadhu.NLC: vaarakkanakkil thodarum velai niruththa poraattam - Jeeva thozhirsangakkorikkaihal niraiveruma?! En.EL.Si.EN.EL.Si-yin surangam-II 1994-um aandu, sutruchchuzhal thaakka mathippeettin (EIA) keezh sutruchchuzhal anumathi petrirundhadhu. Adhanaal,

Meendum sutruchchuzhal thaakka madhippeettukku vinnappikka vendiya avasiyam irundhathu. Aanaal, N.L.C. niruvanam andha anumathiyai pera villai. Irudhiyaaga Chennai uyarn neethimandratthil ivvivakaaram theerkappattu, 2023 September maadhamthaan N.L.C-yin vinnappam parisheelanaikku eerkappattadhu. 2006-2016 varai anumathi peramaale indha niruvanam iyangiyirukkiradhu. Surangam-I-kku vazhangappatta sutruchchuzhal anumathiyin nipandhanaigalpadi, surangam thondumbodhu edukappadum mann, paarai ullithavatrai 20 meetar uyarththirku 28 degree sarivu irukkumpadiyagathaan kotta vendum. Aanaal, vithigalukku purambaga 50 meetar uyarththukku mann kottappattirukkiradhu.

Adhikappadiyana mazaippozhuvu erpattal andha man kuviya sarinthu vizhum apayamiruppadaga CAJ kurippittirukkiradhu. Adhe pola, surangam II-kku vazhangappatta sutruchuzhal anumatihinpadi kottappadum man matrum paaragalin uyaram 65 meter matrum 28 degree sarivu enra alavait thaandakkoodaadhu. Aanaal, innipanthanaikku maaraga 120 meter uyarthukku man kottappattulladhu. Idhan kaaranamaaga man sarinthu arugilulla kaalvai matrum vivasaaya nilangalai moodiyirukkiradhu. N.L.C NLC vivakaaram: Vedhanai therivitha neethipathi... Vilainilangalil thodarum virivaakkap panigal - nadappadhu enna?! 2012, 2013, 2015, 2018 aghiya aandugalil N.L.C niruvanatthin alatchiyathaal thodarum ithuporndha vipaththukkal thodarnthullana.

Vivasayigalin thodar poraattathirkup piragu Rs. 2.18 kodi alavilaana izhappeettai N.L.C niruvanam vivasayigalukku vazhangiyulladhu. Surangangalil nilathai thoandavum, nilakkariyai aLlavum, kondu sellavum periya alavilaana sirappu suranga iyandhirangal (Specialised Mining Equipment – SME) payanpaduthappadugindrana. Ivatrin aayudkaalam 1,00,000 mudhal 1,37,500 mani vela nerangal thaan. Kaalavathiyana iyandhirangalai puthuuyiraakkam seithu, kooduthalaga 15 aandugal varai payanpaduthikkollalaam ena N.L.C nirvaagam mudiveduthirundhadhu. Aanaal,

Moththamulla 72 SME iyandhirangalil 26 SME iyandhirangal evvalavu manineram payanpaduthappattana enra kanakke paraamarikkappadavillai. En. El. Simeelum kanakkugal paraamarikkappatta 46 SME iyandhirangalil 15 SME iyandhirangal kaalavathiyana pinbum puthuyiraakkam seyyappadamal payanpaduthappattullana. 8 SME iyandhirangal kaalavathiyana pinbu 11 aandugal kazhithe puthuyiraakkam seyyappattullana. 4 SME iyandhirangal kaalavathiyana pinnar puthuyiraakkam seyyappattu adhan pinnar 15 aandugal niraivadainda pinnarum payanpaduthappattullana.

1961 matrum 1966 idai patta kaalathil 2 SME iyandhirangalukku badhilaga maatru iyandhirangal vaangappatta pinnarum avai payanpaduthappattullana. Kaalavathiyana iyandhirangalal N.L.C surangangalil palamurai vipaththugal nadandirukkindrana. Ithu thodarbaaga 2009 aam aandu surangap paadhugappu thalaivar nadathiya aayvil 'muraiyaga paraamarikkappadatha iyandhirangalalthaan vipaththugal erpattu uyirilappugal nadandhana' enath theriyavandhathu. 12 kaalavathiyana iyandhirangalukku paadhugappu aayve nadathappadavillai endra athirchchi thagavalum CAG arikkaiyil kurippittirukkirathu. Ithumattumallamal, N.L.C niruvanatthal surangam thonduththaraga adaiyaalam kaanappatta 12,835 hektaril 9,180 hektar nilaththai mattume N.L.C.

Kaiyagapaduththiyulladhu. Maarch 2023 nilavarappadi idhil 5,880.34 hektar nilaththai thondivittadhu. 3,253.47 hektar nilam man kottuvatharkup payanpaduththappattadhu. Idhanpadi paarthaal 46.19 hektar nilam mattume innum thondappadamal ulladhu. NLC: 25,000 ekkar kaiyagam: N.L.C-yaal ennaenna pirachanaigal? - poradum makkal solvadhenna?! Poovulagin nanbargal Sundarrajan. Innum nilam kaiyagapadutha N.L.C. muyarchigal merkolvadhaga thagaval kidaikkindrana. Yerkenave indha niruvanatthukku nilam vazhangha sutru vattara makkal kadum ethirppu theriviththuvarkindrana. Neiveliyil seyalpadum moondru analmin nilaiyangalilum ulla kuraipadugalal avatrai muzh uṟpaththith thiranukku iyakka mudiyavillai enak kandariyappattadhu.

Idhanal moththamaaga Rs. 2,353.99 kodi izhappu erpatthulladhu. Immundru analmin nilaiyangalilum erpattha kolaarugalin kaaranamaaga mattum 6 aandugalil 742 murai min utpaththi niruththappattulladhu. Idhanal 14,538.66 MU minsaara utpaththi izhappu erpatthulladhu. ENL.C. analmin nilaiyangalil 2001, 2016, 2017, 2019 aagiya aandugalil moththam 4 thee vipaththugal nadandhana. 2020 aam aandu nigazhnda iru vipaththugalil mattum 20 per uyirilandhanar. Ithu kuriththu nadaththappatta aayvil, 'Adhiga veppamaana lignite thoosugalai uriya muraiyil agarraamal vittadhudhaan thee vipaththukkuk kaaranam' ena C.A.G kurippittulladhu. Thodarchchiyaaga lignite thoosugalai agarri vandhirundhaal ivvipaththugalai thaduththirukkalaam. Ithu muzhukka muzhukku ENL.C.

Nirvaagaththin alatchiyaththaal mattume nigazhndha vipaththugal. En. El. Sioru pothuthurai niruvanam eppadiyellaam poruppatra muraiyil alatchiyaththudan seyalpadak koodaadho appadiyellaam seyalpattu vandhulladhu En. El. Si. niruvanam. Indha niruvanaththukkuth thangal nilangalai vazhangiya vivasaayigal, ennatra thunbangalais santhiththu neethi kaettup poraadi varugindranaar. Vidhimeeral seyalpaadugalal sutriyaulla graamangalin manvalaththaiyum neervalaththaiyum keduthu makkalin arokkiyaththukku achchuruththalaaga iyangivarum En. El. Si. meedhu arasu nadavadikkai edukka vendum" enak kurippittaar. "Ulagha naadugaludan pottiyidum alavukku Thamizhnaadu valarnthirukkiradhu!" - Staalin perumidham


Tamil

மத்திய அரசின் பொதுத்துறை நிறுவனமான நெய்வேலி நிலக்கரி நிறுவனம் (NLC India Ltd), கடந்த சில ஆண்டுகளாகப் பல்வேறு சுற்றுச்சூழல் விதிமீறல்களில் ஈடுபட்டுள்ளதாகக் குற்றம்சாட்டப்படுகிறது.

இது தொடர்பாக 2017-18 முதல் 2022-23 வரையிலான காலகட்டத்தில் என்.எல்.சி நிறுவனத்தின் செயல்பாடுகளை இந்தியத் தலைமை கணக்குக் கட்டுப்பாட்டாளர் (CAG) ஆய்வு செய்தது. அந்த ஆய்வின் முடிவை இந்த மாதம் நாடாளுமன்றத்தில் ஆதாரங்களுடன் சமர்ப்பித்திருக்கிறது.

அந்த அறிக்கையில், `தமிழ்நாட்டின் கடலூர் மாவட்டத்திலும், ராஜஸ்தானிலும் நிலக்கரிச் சுரங்கங்கள் மற்றும் அனல்மின் நிலையங்களை இயக்கி வரும் என்.எல்.சி நிறுவனம், உரிய சுற்றுச்சூழல் அனுமதியின்றிச் செயல்பட்டது முதல், அனல்மின் நிலையங்களை முறையாகப் பராமரிக்கத் தவறியது வரை பல விதிமீறல்களைச் செய்துள்ளது’ எனத் தெரிவிக்கப்பட்டிருக்கிறது.

என்.எல்.சி
என்.எல்.சி

‘சிஏஜி அறிக்கையில் என்னென்ன விவகாரங்கள் குறிப்பிடப்பட்டிருக்கின்றன’ என்ற கேள்வியுடன் பூவுலகின் நண்பர்கள் அமைப்பின் சுந்தர ராஜனைத் தொடர்புகொண்டோம்.

இந்தப் பிரச்னையின் தீவிரத்தன்மையை விரிவாகப் பேசத் தொடங்கிய சுந்தர ராஜன், “நெய்வேலி நிலக்கரி நிறுவனம் பழுப்பு நிலக்கரிச் சுரங்கங்கள், அனல்மின் நிலையங்கள் உள்ளிட்டவற்றை தமிழ்நாட்டின் கடலூர் மாவட்டத்தின் நெய்வேலியிலும், ராஜஸ்தான் மாநிலத்தின் பார்சிங்கரிலும் இயக்கி வருகிறது.

இந்த நிறுவனத்தின் 2017 -18 முதல் 2022 -23 ஆண்டுகளுக்கு இடையேயான செயல்பாடுகளை சிஏஜி ஆய்வு செய்து, அந்த அறிக்கையை பிப்ரவரி மாதம் நாடாளுமன்றத்தில் சமர்ப்பித்தது. அதில் பல்வேறு குற்றச்சாட்டுகளை ஆதாரத்துடன் அம்பலப்படுத்தியிருக்கிறது சிஏஜி.

2017-ம் ஆண்டு உச்ச நீதிமன்றம், `1994-ம் ஆண்டு வெளியான சுற்றுச்சூழல் தாக்க மதிப்பீட்டு அறிவிக்கையின் கீழ், சுற்றுச்சூழல் அனுமதி பெற்ற அனைத்துத் திட்டங்களுக்கும், 2006இல் வெளியான சுற்றுச்சூழல் தாக்க மதிப்பீட்டு அறிவிக்கையின் கீழ் மீண்டும் அனுமதி பெற வேண்டும்’ என உத்தரவிட்டிருந்தது.

என்.எல்.சி
என்.எல்.சி

என்.எல்.சி-யின் சுரங்கம்-II 1994-ம் ஆண்டு, சுற்றுச்சூழல் தாக்க மதிப்பீட்டின் (EIA) கீழ் சுற்றுச்சூழல் அனுமதி பெற்றிருந்தது. அதனால், மீண்டும் சுற்றுச்சூழல் தாக்க மதிப்பீட்டுக்கு விண்ணப்பிக்க வேண்டிய அவசியம் இருந்தது.

ஆனால், என்.எல்.சி. நிறுவனம் அந்த அனுமதியைப் பெறவில்லை. இறுதியாக சென்னை உயர் நீதிமன்றத்தில் இவ்விவகாரம் தீர்க்கப்பட்டு, 2023 செப்டம்பர் மாதம்தான் என்.எல்.சி-யின் விண்ணப்பம் பரிசீலனைக்கு ஏற்கப்பட்டது. 2006-2016 வரை அனுமதி பெறாமலே இந்த நிறுவனம் இயங்கியிருக்கிறது.

சுரங்கம்-I-க்கு வழங்கப்பட்ட சுற்றுச்சூழல் அனுமதியின் நிபந்தனைகள்படி, சுரங்கம் தோண்டும்போது எடுக்கப்படும் மண், பாறை உள்ளிட்டவற்றை 20 மீட்டர் உயரத்திற்கு 28 டிகிரி சரிவு இருக்கும்படியாகத்தான் கொட்ட வேண்டும். ஆனால், விதிகளுக்குப் புறம்பாக 50 மீட்டர் உயரத்துக்கு மண் கொட்டப்பட்டிருக்கிறது. அதிகப்படியான மழைப்பொழிவு ஏற்பட்டால் அந்த மண் குவியல் சரிந்து விழும் அபாயமிருப்பதாக சிஏஜி குறிப்பிட்டிருக்கிறது.

அதே போல, சுரங்கம் II-க்கு வழங்கப்பட்ட சுற்றுச்சூழல் அனுமதியின்படி கொட்டப்படும் மண் மற்றும் பாறைகளின் உயரம் 65 மீட்டர் மற்றும் 28 டிகிரி சரிவு என்கிற அளவைத் தாண்டக்கூடாது. ஆனால், இந்நிபந்தனைக்கு மாறாக 120 மீட்டர் உயரத்துக்கு மண் கொட்டப்பட்டுள்ளது. இதன் காரணமாக மண் சரிந்து அருகிலுள்ள கால்வாய் மற்றும் விவசாய நிலங்களை மூடியிருக்கிறது.

என்.எல்.சி
என்.எல்.சி

2012, 2013, 2015, 2018 ஆகிய ஆண்டுகளில் என்.எல்.சி நிறுவனத்தின் அலட்சியத்தால் தொடர்ந்து இதுபோன்ற விபத்துக்கள் தொடர்ந்துள்ளன. விவசாயிகளின் தொடர் போராட்டத்திற்குப் பிறகு ரூ. 2.18 கோடி அளவிலான இழப்பீட்டை என்.எல்.சி நிறுவனம் விவசாயிகளுக்கு வழங்கியுள்ளது.

சுரங்கங்களில் நிலத்தைத் தோண்டவும், நிலக்கரியை அள்ளவும், கொண்டு செல்லவும் பெரிய அளவிலான சிறப்புச் சுரங்க இயந்திரங்கள் (Specialised Mining Equipment – SME) பயன்படுத்தப்படுகின்றன. இவற்றின் ஆயுட்காலம் 1,00,000 முதல் 1,37,500 மணி வேலை நேரங்கள்தான்.

காலாவதியான இயந்திரங்களைப் புத்துயிராக்கம் செய்து, கூடுதலாக 15 ஆண்டுகள் வரை பயன்படுத்திக்கொள்ளலாம் என என்.எல்.சி நிர்வாகம் முடிவெடுத்திருந்தது. ஆனால், மொத்தமுள்ள 72 SME இயந்திரங்களில் 26 SME இயந்திரங்கள் எவ்வளவு மணிநேரம் பயன்படுத்தப்பட்டன என்கிற கணக்கே பராமரிக்கப்படவில்லை.

என்.எல்.சி
என்.எல்.சி

மேலும் கணக்குகள் பராமரிக்கப்பட்ட 46 SME இயந்திரங்களில் 15 SME இயந்திரங்கள் காலாவதியான பின்பும் புத்துயிராக்கம் செய்யப்படாமல் பயன்படுத்தப்பட்டுள்ளன. 8 SME இயந்திரங்கள் காலாவதியான பின்பு 11 ஆண்டுகள் கழித்தே புத்துயிராக்கம் செய்யப்பட்டுள்ளன.

4 SME இயந்திரங்கள் காலாவதியான பின்னர் புத்துயிராக்கம் செய்யப்பட்டு அதன் பின்னர் 15 ஆண்டுகள் நிறைவடைந்த பின்னரும் பயன்படுத்தப்பட்டுள்ளன. 1961 மற்றும் 1966 இடைப்பட்ட காலத்தில் 2 SME இயந்திரங்களுக்குப் பதிலாக மாற்று இயந்திரங்கள் வாங்கப்பட்ட பின்னரும் அவை பயன்படுத்தப்பட்டுள்ளன.

காலாவதியான இயந்திரங்களால் என்.எல்.சி சுரங்கங்களில் பலமுறை விபத்துகள் நடந்திருக்கின்றன. இது தொடர்பாக 2009 ஆம் ஆண்டு சுரங்கப் பாதுகாப்புத் தலைவர் நடத்திய ஆய்வில் ‘முறையாகப் பராமரிக்கப்படாத இயந்திரங்களால்தான் விபத்துகள் ஏற்பட்டு உயிரிழப்புகள் நடந்தன’ எனத் தெரியவந்தது. 12 காலாவதியான இயந்திரங்களுக்குப் பாதுகாப்பு ஆய்வே நடத்தப்படவில்லை என்ற அதிர்ச்சித் தகவலும் சிஏஜி அறிக்கையில் குறிப்பிட்டிருக்கிறது.

இதுமட்டுமல்லாமல், என்.எல்.சி. நிறுவனத்தால் சுரங்கம் தோண்டுவதற்காக அடையாளம் காணப்பட்ட 12,835 ஹெக்டரில் 9,180 ஹெக்டர் நிலத்தை மட்டுமே என்.எல்.சி. கையகப்படுத்தியுள்ளது. மார்ச் 2023 நிலவரப்படி இதில் 5,880.34 ஹெக்டர் நிலத்தைத் தோண்டிவிட்டது. 3,253.47 ஹெக்டர் நிலம் மண் கொட்டுவதற்குப் பயன்படுத்தப்பட்டுள்ளது. இதன்படி பார்த்தால் 46.19 ஹெக்டர் நிலம் மட்டுமே இன்னும் தோண்டப்படாமல் உள்ளது.

பூவுலகின் நண்பர்கள் சுந்தர்ராஜன்
பூவுலகின் நண்பர்கள் சுந்தர்ராஜன்

இன்னும் நிலம் கையகப்படுத்த என்.எல்.சி. முயற்சிகள் மேற்கொள்வதாக தகவல் கிடைக்கின்றன. ஏற்கெனவே இந்த நிறுவனத்துக்கு நிலம் வழங்க சுற்று வட்டார மக்கள் கடும் எதிர்ப்பு தெரிவித்துவருகின்றனர்.

நெய்வேலியில் செயல்படும் மூன்று அனல்மின் நிலையங்களிலும் உள்ள குறைபாடுகளால் அவற்றை முழு உற்பத்தித் திறனுக்கு இயக்க முடியவில்லை எனக் கண்டறியப்பட்டுள்ளது. இதனால் மொத்தமாக ரூ. 2,353.99 கோடி இழப்பு ஏற்பட்டுள்ளது. இம்மூன்று அனல்மின் நிலையங்களிலும் ஏற்பட்ட கோளாறுகளின் காரணமாக மட்டும் 6 ஆண்டுகளில் 742 முறை மின் உற்பத்தி நிறுத்தப்பட்டுள்ளது. இதனால் 14,538.66 MU மின்சார உற்பத்தி இழப்பு ஏற்பட்டுள்ளது.

என்.எல்.சி. அனல்மின் நிலையங்களில் 2001, 2016, 2017, 2019 ஆகிய ஆண்டுகளில் மொத்தம் 4 தீ விபத்துகள் நடந்தன. 2020 ஆம் ஆண்டு நிகழ்ந்த இரு விபத்துகளில் மட்டும் 20 பேர் உயிரிழந்தனர்.

இது குறித்து நடத்தப்பட்ட ஆய்வில், ‘அதிக வெப்பமான லிக்னைட் தூசுகளை உரிய முறையில் அகற்றாமல் விட்டதுதான் தீ விபத்துக்குக் காரணம்’ என சி.ஏ.ஜி குறிப்பிட்டுள்ளது. தொடர்ச்சியாக லிக்னைட் தூசுகளை அகற்றி வந்திருந்தால் இவ்விபத்துகளைத் தடுத்திருக்கலாம். இது முழுக்க முழுக்க என்.எல்.சி. நிர்வாகத்தின் அலட்சியத்தால் மட்டுமே நிகழ்ந்த விபத்துகள்.

என்.எல்.சி
என்.எல்.சி

ஒரு பொதுத்துறை நிறுவனம் எப்படியெல்லாம் பொறுப்பற்ற முறையில் அலட்சியத்துடன் செயல்படக் கூடாதோ அப்படியெல்லாம் செயல்பட்டு வந்துள்ளது என்.எல்.சி. நிறுவனம். இந்த நிறுவனத்துக்குத் தங்கள் நிலங்களை வழங்கிய விவசாயிகள், எண்ணற்ற துன்பங்களைச் சந்தித்து நீதி கேட்டுப் போராடி வருகின்றனர்.

விதிமீறல் செயல்பாடுகளால் சுற்றியுள்ள கிராமங்களின் மண்வளத்தையும் நீர்வளத்தையும் கெடுத்து மக்களின் ஆரோக்கியத்துக்கு அச்சுறுத்தலாக இயங்கிவரும் என்.எல்.சி. மீது அரசு நடவடிக்கை எடுக்க வேண்டும்” எனக் குறிப்பிட்டார்.


மூலதளம்: India News
Click the link above to read the full article on the original website.

More From Author

NLC: The ‘Tunnel’ of Violations at NLC? Shocking Revelations in the CAG Report; An Analysis

‘Target South’ – Adhav goes to Chennai; Kongu goes to Sengottaiyan! – Vijay hands over the election responsibility!